Resale Flats

3 rooms @ (S$18,788.00) | 4 rooms @ (S$20,788.00)| 5 rooms @ (S$22,588.00)| Executive @ (S$24,588.00)

Professional Services

  1. Design Consultation
  2. Space Planning
  3. Perspective Drawings
  4. Material & Colour Proposal
  5. Project management
  6. Site Supervision

Demolition Works

  1. Demolish existing flooring for Living & Dining
  2. Demolish existing flooring for Store & Bedrooms
  3. Demolish existing flooring for Kitchen
  4. Demolish existing wall tiles for Kitchen
  5. Demolish existing flooring for 02 Bathrooms
  6. Demolish existing wall tiles for 02 Bathrooms
  7. Demolish existing skirtings for Whole unit
  8. Dismantle existing sanitary wares & accessories for 02 Bathrooms
  9. Haulage service & debris disposal

Masonry Works

  1. Homogenous flooring (600mm x 600mm) c/w skirting at Living & Dining
  2. Laminated flooring c/w skirting at All Bedrooms
  3. Ceramic wall tiles till ceiling height for Kitchen
  4. Homogenous non-slip flooring at Kitchen
  5. Waterproofing membrane for Kitchen
  6. Ceramic wall tiles till ceiling height for Main Bathroom
  7. Ceramic wall tiles till ceiling height for Common Bathroom
  8. Homogenous non-slip flooring at Main Bathroom
  9. Homogenous non-slip flooring at Common Bathroom
  10. Waterproofing membrane for 02 Bathrooms
  11. 50mm cabinet base c/w side tiles finish
  12. 50mm fridge base c/w tiles finish
  13. 50mm washing machine base c/w tiles finish
  14. 50mm shower kerb c/w tiles finish at Main Bathroom

Plumbing Works

  1. Standard cold copper piping for Whole unit
  2. Connection of inlet & outlet piping for kitchen sink
  3. Supply & install 02 sets of standard water closet
  4. Supply & install 02 sets of standard wash basins & cold taps (w/o pedestal)
  5. Provide labour to install accessories for 02 bathrooms
  6. Provide labour to install 01 no. of instant water heater

Ceiling Works

  1. L-box light holder at Living
  2. False ceiling at Dining
  3. False ceiling at Foyer
  4. False ceiling at Bedrooms’ passageway

Kitchen Cabinet

  1. L20ft run laminated ply kitchen cabinet with ABS door trimmings
  2. L10ft solid surface kitchen worktop
  3. 01 no. of 2-tier stainless steel dish drainer
  4. Imported designer handles
  5. 01 no. of cultery tray
  6. Labour to install cooker hood & hob

Miscellaneous Works

  1. Painting of whole unit (wall & ceiling) with ICI emulsion paint
  2. Painting of all pipes, doors, door frames & main gate with ICI gloss paint
  3. Re-varnishing of existing main door
  4. Corrugated paper floor board protection for existing flooring
  5. General cleaning upon completion